The Nuclear fall outage season will not be as robust as the spring season but will have plenty of working opportunities for our members.
Both APM and Siemens are expected to have multiple outages during the fall season. The tentative schedule is as follows:
APM
Plant Vogtle will need a total of 55 millwrights for a first call out in late August.
Oconee will need a total of 30 millwrights for a first call in early October.
Hatch mobilization and setup for next spring will have a first call of early November.
Siemens
McGuire will need a total of 20 millwrights with an early September report date.
Turkey Point will need a total of 73 millwrights with an early September report date.
Farley will need a total of 60 millwrights with an early September report date.
Waterford will need a total of 92 millwrights with a mid-August report date.
Comanche Peak will need a total of 70 millwrights with late September report date.
If you’re not registered for the text dispatch, now would be a great time to register. You will need your UBC ID and pin to complete the registration. Members registered for the text dispatch notifications will be notified about work in their area before a call dispatch is sent out. To register, click here.
If you have any questions, contact Steve Williams (615) 474-9696